Located in the Pretoria CBD, close to the Union Buildings, Agrivaal was the first public sector building to obtain a Green Star Design rating in 2012. Following environmentally innovative refurbishments of the Agrivaal heritage building and construction of the new office building on the site, Batho Pele House achieved a four-star Green Star SA Office v1 – As Built rating from the Green Building Council South Africa (GBCSA).
The site was chosen by the Department of Public Works (DPW) as the building is situated in the heart of the Pretoria CBD, integrated into an old network and the growing new metropolis of public transport in the area, with the Gautrain and the Rea Vaya Bus Rapid Transit System (BRT) – offering easy transit for all the building’s occupants and bringing people back into this once derelict part of the CBD. This has also been a long-term project; in 2010 a tender was issued for the sustainable design of the building. The tenant for the building, the Department of Public Service and Administration (DPSA), was only later confirmed - the designs had to be flexible and underwent several rounds of changes to allow for the tenant’s requirements.
Along with achieving four-star Green Star credentials, importance was placed on restoring and protecting the heritage of the existing Agrivaal building, as well as designing the easy transition between the new 10-storey building.
For this project, WSP formed part of a design team, Akani Consortium, inclusive of a project manager, quantity surveyor and architect – with multi-disciplinary technical skills and services provided by WSP, including full scope of engineering (across structural, civil, electrical, mechanical, lifts, fire, electronic, wet services etc.) and sustainability consulting.
Roxanne Dovey, sustainability consultant, WSP, Building Services, Africa, says: “The Agrivaal building and site was already owned by DPW and from the client’s point of view, there was never any doubt on the desire to have a sustainable building. Green or sustainable building considerations were included in the early concepts for the building, during design. This was not only a bold step by DPW, but works very well for the entire design team, as the earlier sustainability is given consideration on a project, greater positive impacts and results for an efficient building can be achieved.”
The formal designs for the new building were forged around the time the country’s initial carbon emissions reduction target of 34% by 2020 were pledged in 2010. The following year the country hosted the Conference of the Parties (COP 17) meeting in Durban, during which discussions were tabled on potential regulations for all buildings to become more green and sustainable.
“The approach and perseverance by DPW on this project demonstrates that they are on the cusp of pushing the national agenda – by doing their bit to reduce carbon emissions through their built assets, as well as to ensure that the new building is future-proofed for generations to come,” adds Dovey.
Some of the heritage-sensitive and environmentally innovative features of this project include:
“This was a challenging project, especially given the time from when it commenced, to construction and then occupation – which was longer than usually experienced with commercial building projects. Over this time the design team needed to closely monitor the sustainability aspects through changes in both the designs and people involved in the project to ensure consistency was maintained and that we achieved compliance and met the criteria for the four-star Green Star rating,” indicates Dovey.
“That said, it’s been an incredible project to be involved with – one that has set a benchmark for public sector buildings in South Africa. And, in time, we expect the investment by DPW into the CBD will not only have positive social and economic sustainability spin-offs, but will rejuvenate an important business node as part of the long-term strategy to revitalise Tshwane,” concludes Dovey.